13. Multiple IRRs for a particular project can occur when there is (are): (Point
ID: 2739376 • Letter: 1
Question
13. Multiple IRRs for a particular project can occur when there is (are): (Points : 3) large abandonment costs at the end of a project's life
a major shutdown and rebuilding of a facility sometime during its life
more than one sign change in the pattern of cash flows over a project's life.
all of the above are correct
cash flows after the payback period are ignored in the calculation
payback ignores the time value of money
payback fails to provide an objective decision-making criterion
all of the above
greater than 0
greater than or equal to 1
greater than 1.1
Explanation / Answer
13 All the above are correct
multiple IRRs occur when there exists negative cash flows during the project life other than initial investment costs.
there should be even one negative cash flow to get more than 1 IRR.
.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.