You are considering two independent projects, project A and project B. The initi
ID: 2734520 • Letter: Y
Question
You are considering two independent projects, project A and project B. The initial cash outlay associated with project A is $60, 000, and the initial cash outlay associated with project B is $80, 000. The required rate of return on both projects is 9 percent. The expected annual free cash inflows from each project are in the popup window: Calculate the NPV for each project and indicate if the project should be accepted. What is the PI of project A? What is the PI of project B? Based on the PI criterion, project A should be because its PI is than 1.00 and project B should be because its PI is than 1.00.Explanation / Answer
PI = Present value of cash inflows / Initial cash outlay
Project A:
Present value of cash inflows = Annual cash inflows x PVIFA 9%, 6 years = $ 12,000 x 4.4859 = $ 53,831
PI = 53,831 / 60,000 = 0.90
Project B:
Present value of cash inflows = $ 13,000 x 4.4859 = $ 58,317
PI = 58,317 / 80,000 = 0.73
Project A should be rejected as its PI is less than 1, and Project B should also be rejected as its PI is also less than 1.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.