pEASE DO NOT USE AN EXCEL SPREAD SHEET i NEED TO UNDERSTAND YOUR STEPS Please pr

ID: 2723906 • Letter: P

Question

pEASE DO NOT USE AN EXCEL SPREAD SHEET i NEED TO UNDERSTAND YOUR STEPS

Please provide a formular for me to follow example PVF ....

I also need a graph or a time line profile 13. NPV versus IRR. Here are the cash flows for two mutually exclusive projects: (LO8-1 and LO8-2)

Project

C0 C1 C2 C3

A -$20,000 +$8,000 +$8,000 +$ 8,000

B - 20,000 0 0 + 25,000

a. At what interest rates would you prefer project A to B? ( Hint: Try drawing the NPV profile of each project.) .

b.What is the IRR of each project?

This is my second request I can not understand the spread sheet on excel

Explanation / Answer

We will first find the IRR of each project using excel

We use the IRR function to find the IRR, the IRR is calculated using =irr(cash_flow)

The IRR of project A is aas follows

The IRR for project B is as follows:

(a) At no point in time would we prefer project A over project B since IRR of B is lower tha that of A and we would always prefer B over A

(b) The IRR of A is : 9.70% and IRR of B is 7.72%

Project A 0 -20000 1 8000 2 8000 3 8000 IRR 9.70%