Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Scanlin, Inc., is considering a project that will result in initial aftertax cas

ID: 2714300 • Letter: S

Question

Scanlin, Inc., is considering a project that will result in initial aftertax cash savings of $1.76 million at the end of the first year, and these savings will grow at a rate of 3 percent per year indefinitely. The firm has a target debt–equity ratio of 0.85, a cost of equity of 11.6 percent, and an aftertax cost of debt of 4.4 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective approach and applies an adjustment factor of 1 percent to the cost of capital for such risky projects. What is the maximum initial cost the company would be willing to pay for the project? (Enter your answer in dollars, not millions of dollars, i.e. 1,234,567. Do not round intermediate calculations and round your final answer to the nearest whole dollar amount.)

Explanation / Answer

WACC = Wd×Rd×(1-t)+ We×Ke

W is weights of respective portfolios

R is return on respective portfolios

= (0.85÷1.85)×4.4%+(1÷1.85)×11.6%

= 8.29%

Relevant required rate is 9.29% (8.29%+1%).

Maximum cost that company will pay:

= $1.76 million÷(9.29%-3%)

= $27,980,922

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote