OPTIMAL CAPITAL BUDGET Hampton Manufacturing estimates that is WACC is 12 %. The
ID: 2713461 • Letter: O
Question
OPTIMAL CAPITAL BUDGET
Hampton Manufacturing estimates that is WACC is 12 %.
The company is considering the following seven investment projects:
Project Size IRR
A $750,000 14.0%
B 1,250,000 13.5
C 1,250,000 13.2
D 1,250,000 13.0
E 750,000 12.7
F 750,000 12.3
G 750,000 12.2
A. Assume that each of these projects is independent and that each is just as risky as the firm's existing assets. Which set of projects should be accepted, and what is the firm's optimal capital budget?
B. Now assume that Projects C and D are mutually exclusive. Project D has an NPV of $400,000, whereas Project C has an NPV of $350,000. Which set of projects should be accepted, and what is the firm's optimal capital budget?
C. Ignore part b and now assume that each of the projects is independent but that management decides to incorporate project risk differentials. Management judges projects B,C,D, and E to have average risk, Project A to have high risk, and projects F and G to have low risk. The company adds 2 percent to the WACC of those projects that are significantly more risky than average, and it subtracts 2 percent from the WACC for those that are substantially less risky than average. Which set of projects should be accepted, and what is the firm's optimal capital budget?
Explanation / Answer
The marginal cost of capital (MCC) is defined as the cost of the last dollar of new capital the firm raises, and the marginal cost rises as more and more capital is raised during a given period.
since the captial structure is not given let us assume that the marginal cost of captial of the company 12.8, in this scenario the following projects could be accepted:
firms optimal capital budget is $ 4,500,000.
B) Project D which has a higher NPV of $ 400,000 can be preferred over project C:
C)
Project Size IRR A $750,000 14.0% B 1,250,000 13.5 C 1,250,000 13.2 D 1,250,000 13.0Related Questions