At NYIT in 1993 a 100ton electric A/C system (electric driven compressor) with a

ID: 2710451 • Letter: A

Question

At NYIT in 1993 a 100ton electric A/C system (electric driven compressor) with a 100ton natural gas absorption system. Electric then was $.12/kwh and the natural gas unit was expected to half the energy cost. Other date is listed below. Make a financial analysis and decide if a replacement is worth it. Lifespan of electric system=10 years and salvage S=0; Lifespan of the absorption system is 20 years and S=0(even after 10years) Energy savings = 50% of electric; Maintenance Cost/yr,Electric $2000/yr, gas $6000/yr: Initial cost of electric=0 (sunk cost), gas $60,000 and the installation is additional. $20,000. Gov’t funding is 30% of the initial cost. The interest rate is 6% and the air-conditioning system operates on average 1000hrs/yr. The may assume any other unknown factors. On a quantitative basis is the switch justified. Work the problem out either on a present value basis for 10 years or annuitized cost per year for the same time period.

Explanation / Answer

Replacement is worth if adopted for 20 year span, If we are looking replacement for 10 year horizon, we are putting excess investment of $21,839.48 (Present Value) but for 20 year span if all the cost factors remain same, replacement is worth.

Cost Analysis

100ton electric A/C system

100ton natural gas absorption system

Lifespam

10 Year

20 year

Salvage Value

$0.00

$0.00

Maintenance Cost

$2,000.00

$6,000.00

Initial cost

$0.00

$60,000.00

Installation

$0.00

$20,000.00

Govt Funding

$18,000.00

PV of Operating Cost for 10 Year 6%

$88,321.04

$44,160.52

Cost of the project for 10 Year

$90,321.04

$112,160.52

PV of Operating Cost for 20 Year 6%

$137,639.05

$68,819.53

Cost of the project for 20 Year

$139,639.05

$136,819.53

Operating Cost Every year

      Per Unit cost (1 Ton consums 1 Kw)

$0.12 Per Kw

$0.06 Per Kw

      Cost for 100 Ton

$12.00

$6.00

     Annual Cost (1000 Hr Usage)

$12,000.00

$6,000.00

Cost Analysis

100ton electric A/C system

100ton natural gas absorption system

Lifespam

10 Year

20 year

Salvage Value

$0.00

$0.00

Maintenance Cost

$2,000.00

$6,000.00

Initial cost

$0.00

$60,000.00

Installation

$0.00

$20,000.00

Govt Funding

$18,000.00

PV of Operating Cost for 10 Year 6%

$88,321.04

$44,160.52

Cost of the project for 10 Year

$90,321.04

$112,160.52

PV of Operating Cost for 20 Year 6%

$137,639.05

$68,819.53

Cost of the project for 20 Year

$139,639.05

$136,819.53

Operating Cost Every year

      Per Unit cost (1 Ton consums 1 Kw)

$0.12 Per Kw

$0.06 Per Kw

      Cost for 100 Ton

$12.00

$6.00

     Annual Cost (1000 Hr Usage)

$12,000.00

$6,000.00