accept project A as it always has the higher NPV accept project B as it always h
ID: 2708540 • Letter: A
Question
accept project A as it always has the higher NPV accept project B as it always has the higher NPV accept A at 8.5 percent and B at 13 percent accept B at 8.5 percent and A at 13 percent accept B at 8.5 percent and neither at 13 percent You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What if the discount rate is 13 percent? accept project A as it always has the higher NPV accept project B as it always has the higher NPV accept A at 8.5 percent and B at 13 percent accept B at 8.5 percent and A at 13 percent accept B at 8.5 percent and neither at 13 percentExplanation / Answer
NPV at 8.5%
Project A= -80000+31000/1.085+31000/1.085^2+31000/1.085^3= -825.3065
Project B=-80000+110000/1.085^3=6119.891
NPV at 13 %
Project A= -80000+31000/1.13+31000/1.13^2+31000/1.13^3=-6804.2695
Project B=-80000+110000/1.13^3= -3764.4821
So,accept B at 8.5 percent and neither at 13 percent
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.