Petroleum Inc. (PI) controls offshore oil leases. It is considering the construc
ID: 2707101 • Letter: P
Question
Petroleum Inc. (PI) controls offshore oil leases. It is considering the construction of a deep-sea oil rig at a cost of $500 million. The price of oil is $100/bbl. and extraction costs are $50/bbl. PI expects costs to remain constant. The rig will produce an estimated 1,200,000 bbl. per year forever. The risk-free rate is 10% per year, which is also the cost of capital. (Ignore taxes). Suppose that oil prices are uncertain and are equally likely to be $120/bbl. or $80/bbl. next year. Calculate today's NPV of the project (i.e., NPV @ t = 0) if it were postponed by one year.
Explanation / Answer
Since the cash flows are forever, the problem relates to perpetuity.
The formula for present value of perpetuity is
Present value of perpetuity = Annual cash flows / Cost of capital
Annual cash flows = ( Selling price - Cost per bbl) x Number of bbl's per year
= ($100 / bbl - $50 / bbl) x $1,200,000
= $60,000,000 /bbl
Substitute the values in the above formula:
PV of perpertuity = $60,000,000 / 0.1
= $600,000,000
To calculate the NPV of the project,
NPV = Present value of perpetuity - Cost of the project
= $600,000,000 - $500,000,000
= $100,000,000
Therefore, the NPV of the project when t=0 is $100,000,000 or $100 million
Hence the correct option is A) $100,000,000
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.