Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

--------------Initial Outlay--------------------------------------- Net Cash Flo

ID: 2706574 • Letter: #

Question

--------------Initial Outlay--------------------------------------- Net Cash Flow Each Period

------------------------------------------------------------1------------------ 2------------------ 3---------------------- 4

Project A ----$4,000-------------------------- $2,003 -----------$2,003----------- $2,003------------- $2,003

Project B---- $4,000-------------------------------------------------------------------------------------------- $10,736


A. Calculate the net present value of each of the above projects, assuming a 14 percent discount rate.


B. If 14 Percent is the required rate of return for these projects, which project is preferred? Why?

Explanation / Answer

Hi,


Please find the answer as follows:


Part A:


NPV (Project A) = - 4000 + 2003/(1+.14)^1 + 2003/(1+.14)^2 + 2003/(1+.14)^3 + 2003/(1+.14)^4 = 1836.17


NPV (Project B) = - 4000 + 10736/(1+.14)^4 = 2356.57


Part B:


Since NPV of Project B is higher than that of Project A, Project B should be preferred.


Thanks.