--------------Initial Outlay--------------------------------------- Net Cash Flo
ID: 2706574 • Letter: #
Question
--------------Initial Outlay--------------------------------------- Net Cash Flow Each Period
------------------------------------------------------------1------------------ 2------------------ 3---------------------- 4
Project A ----$4,000-------------------------- $2,003 -----------$2,003----------- $2,003------------- $2,003
Project B---- $4,000-------------------------------------------------------------------------------------------- $10,736
A. Calculate the net present value of each of the above projects, assuming a 14 percent discount rate.
B. If 14 Percent is the required rate of return for these projects, which project is preferred? Why?
Explanation / Answer
Hi,
Please find the answer as follows:
Part A:
NPV (Project A) = - 4000 + 2003/(1+.14)^1 + 2003/(1+.14)^2 + 2003/(1+.14)^3 + 2003/(1+.14)^4 = 1836.17
NPV (Project B) = - 4000 + 10736/(1+.14)^4 = 2356.57
Part B:
Since NPV of Project B is higher than that of Project A, Project B should be preferred.
Thanks.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.