For CP2 you will set your CP1 project and document deliverable aside and start f
ID: 2700255 • Letter: F
Question
For CP2 you will set your CP1 project and document deliverable aside and start fresh. Your task is to use this document and the data provided to create a project file using Microsoft Project. The data below will establish a project budget and schedule baseline with Budget = $4,449,920.00 and a highly desired completion date of 12/19/08
The project at this future date shows that our project is not performing very well. However, you are given the opportunity to make some changes to the project to still complete it on the desired date of 12/19/08.
These directions help you set the Gantt to represent the anticipated 50% completion 'date' of 10/1/08. This is the date where the project 'should be' 50% complete. You do NOT set the project to 50% complete, you set it to 40%. These are two different things and these 2 parameters set up the scenario for you to generate EV data and tell me about how the project is doing.
% Complete (The Reality)
The 40% should be set by you by setting the top level task (project name) to 40%. This is how 'done' we are saying we actually are with the project at this point in time.
% Scheduled (The Plan)
The date (i.e. point in time) provided for the review fast forwards the project to the 'anticipated' 50% project scheduled date. This is the date on the calendar when we 'wanted' to be 50% complete.
First, change the project start date to Mon 4/14/08.
Explanation / Answer
First, change the project start date to Mon 4/14/08.
Use the following data to setup your baseline project file. Adjust indenting to match WBS coding provided.In MSP right mouse click the header row and insert a WBS Column as shown. Do not add durations or dates for the Summary Tasks because these will populate for you when you enter the lower task information.
WBS
Task Name
Duration
Start
Finish
Predecessors
1
Theme Park Project
180 days
4/14/2008
12/19/2008
1.1
Site Layout & Site Grading
10 days
4/14/2008
4/25/2008
1.2
Footings & Foundations
55 days
4/28/2008
7/11/2008
2
1.3
Masonry
60 days
5/19/2008
8/8/2008
3SS+15 days
1.4
Frames, Columns and Beams
40 days
7/7/2008
8/29/2008
4SS+35 days
1.5
Joists & Roof Deck
30 days
9/1/2008
10/10/2008
5
1.6
Slab on Grade
35 days
7/14/2008
8/29/2008
3
1.7
Rough Carpentry
35 days
9/1/2008
10/17/2008
7
WBS
Task Name
Duration
Start
Finish
Predecessors
1
Theme Park Project
180 days
4/14/2008
12/19/2008
1.1
Site Layout & Site Grading
10 days
4/14/2008
4/25/2008
1.2
Footings & Foundations
55 days
4/28/2008
7/11/2008
2
1.3
Masonry
60 days
5/19/2008
8/8/2008
3SS+15 days
1.4
Frames, Columns and Beams
40 days
7/7/2008
8/29/2008
4SS+35 days
1.5
Joists & Roof Deck
30 days
9/1/2008
10/10/2008
5
1.6
Slab on Grade
35 days
7/14/2008
8/29/2008
3
1.7
Rough Carpentry
35 days
9/1/2008
10/17/2008
7