Project risk analysis The Butler-Perkins Company (BPC) must decide between two m
ID: 2699856 • Letter: P
Question
Project risk analysis
The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,750 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions:
BPC has decided to evaluate the riskier project at 13% and the less-risky project at 8%.
Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $6,500 0.2 $0 0.6 $6,750 0.6 $6,750 0.2 $7,000 0.2 $19,000Explanation / Answer
1)
0.2*6500 + 0.6*6750 +0.2*7000 = $6750
0.2*0 + 0.6*6750 + 0.2*19000 = $ 7850
2) Question not clear