zelluse corp is considering two mutually exclusive projects, a and b. project a
ID: 2698780 • Letter: Z
Question
zelluse corp is considering two mutually exclusive projects, a
and b. project a cost $50,000 and is expected to generate $38,000
in year one and $30,000 in year two. Project b costs $70,000 and is
expected to generate $24,000 in year one $32,000 in year two,
$23,000 in year three and $29,000 in year four. Zelluose Corp has
required rate of return for these projects is 12%. whixh project would reccomend using the replacement chain method to evaluate the projects with different live?
A) Project B because the replacement chain NPV for project A is only $10,972
B) project A because its replacement chain NPV is $ 14,098, which exceeds the NPV for project B.
C) Project A because its replacment chain NPV is $15,689 which exceeds the NPV for projects B.
D)Project B because its NPV is higher than projects A's NPV.
Explanation / Answer
NPV for project a is -50000 + 38000/1.12 + 30000/1.12^2 = 7844.39
NPV for project b is -70000 + 24000/1.12 + 32000/1.12^2 + 23000/1.12^3 + 29000/1.12^4 = 11739.75
The using replacement chain NPV is 4 year NPV for project A is 7844.39 * 2 = 15,689
Hence
C) Project A because its replacment chain NPV is $15,689 which exceeds the NPV for projects B.