You are comparing two mutually exclusive projects. The crossover point is 12.3 p
ID: 2669917 • Letter: Y
Question
You are comparing two mutually exclusive projects. The crossover point is 12.3 percent. You have determined that you should accept project A if the required return is 13.1 percent. This implies you should: Question 7 options:A) always accept project A.
B) be indifferent to the projects at any discount rate above 13.1 percent.
C) always accept project A if the required return exceeds the crossover rate.
D) accept project B only when the required return is equal to the crossover rate.
E) accept project B if the required return is less than 13.1 percent.
Explanation / Answer
the answer is C the guy above is using the wrong numbers ie crossover point
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.