12-4 Basic scenario analysis Murdock Paints is in the process of evaluating two
ID: 2653308 • Letter: 1
Question
12-4 Basic scenario analysis Murdock Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The firm's financial analysts have developed pessimistic, most likely, and optimistic estimates of the annual cash inflows associated with each project. These estimates are shown in the following table. a. Determine the range of annual cash inflows for each of the two projects. b. Assume that the firm's cost of capital is 10% and that both projects have 20-year lives. construct a table similar to this one for the NPVs for each project. Include the range of NPVs for each project. c. Do parts a and b provide consistent views of the two projects? Explain. d. Which project do you recommend? Why?Explanation / Answer
.Determine the range of annual cash inflows for each of the two projects.
.Determine the range of annual cash inflows for each of the two projects.
Range = Highest value - Lowest value Cash inflows Outcome Project A Project B Pessimistic 200 900 Most likely 1,000 1,000 Optimistic 1,800 1,100 Range = 1,600 200 b.Assume that the firm’ s cost of capital is 10% and that both projects have 20-year lives. Construct a table similar to this for the NPVs for each project. Include the range of NPVs for each project. Calculation of NPV for different outcomes: Project A: Pessimistic: Most likely: Optimistic: Rate = 10% Rate = 10% Rate = 10% Nper = 20 Nper = 20 Nper = 20 PMT = -200 PMT = -1,000 PMT = -1,800 PV =? PV =? PV =? PV = $1,702.71 PV = $8,513.56 PV = $15,324.41 Cash outflow = -8,000 Cash outflow = -8,000 Cash outflow = -8,000 NPV = ($6,297.29) NPV = $513.56 NPV = $7,324.41 Project B: Pessimistic: Most likely: Optimistic: Rate = 10% Rate = 10% Rate = 10% Nper = 20 Nper = 20 Nper = 20 PMT = -900 PMT = -1,000 PMT = -1,100 PV =? PV =? PV =? PV = $7,662.21 PV = $8,513.56 PV = $9,364.92 Cash outflow = -8,000 Cash outflow = -8,000 Cash outflow = -8,000 NPV = ($337.79) NPV = $513.56 NPV = $1,364.92 NPVs of project A and Project B under different outcomes: NPVs Outcome Project A Project B Pessimistic ($6,297.29) ($337.79) Most likely 513.56 513.56 Optimistic 7,324.41 1,364.92 Range = 13,622 1,703Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.