decision has been made to perform certain repairs on the outlet works of a small
ID: 2648048 • Letter: D
Question
decision has been made to perform certain repairs on the outlet works of a small dam. For a particular - Inch gate valve. There are three available Alternatives: Of the valve is replaced; the probability of a failure of valve seats, over the life of the Project is 30%; the of failure of the valve stem is 20%; and of failure of the valve body is 10%. If the valve is repaired; the probability of a failure of valve seats, over the life of the project is 40%; the of failure of the valve stem is 30%; and of failure of the valve body is 20%. If the valve is left as it is; the probability of a failure of valve seats, over the life of the project is 60 %, probability of failure of the valve stem is 50%; and of failure of the valve body is 40%. The present worth of cost of future repairs and service disruption of failure of the seats is $10,000; the of the cost of a failure of stem is $20,000; and The present worth of cost of a failur of the body $30,00; repairing the valve now is $10,000; and replacing it is $20,000 If the criterion is to minimize expected costs, which alternative is best? Explain in deatilExplanation / Answer
In this problem, you have to decide on a poject of damaged valve. It can be repaired, replaced or can be left as it is.
Alternative 1: If it is replaced, then 60% chance of failure is there. so there is 40% probability of it sucess. Out of 60% failure, 30% may be due to valve sheet, 20% due to valve stem and 10% due to valve body .
Now consider cost. replacing cost is $20,000. This cost is a must if repairing is made. Further company has to incur $10,000 if valve sheet has failed. Then total cost will be $20,000+$10,000 = $30,000. Probability of incurring this $30,000 cost is 30%.
If valve stem fail ,then it has to bear an extra cost of $20,000 for repairing stem. Thus total cost will be $20,000+$20,000=$40,000. Its probability is 20%
If valve body fail, then extra cost is $30,000. Thus total cost is $20,000+$30,000= $50,000. It has a probability of 10%.
There is 40% chance that everything will be Ok. In that case total cost will be $20,000 (i.e. replacement cost only).
Hence expected cost of repairing here is:
0.3 x $30,000 +0.2 x $40,000 + 0.1 x $50,000 + 0.4 x $20,000 = $30,000
------------------------------------------------------------------------------------------------------------------------------------------------------
Now consider second alternative: Here repairing of valve is done. It has a cost of $10,000. There is 40% chance of failure of valve sheet. In that case additional $10,000 cost is required. Thus probability of incurring $10,000+$10,000=$20,000 cost is 40%.
After repairing there is 30% chance that valve stem will fail. In that case extra cost of $20,000 is required. Thus probability of incurring a totalcost of $10,000+$20,000=$30,000 is 30%.
Also after repair body of valve may fail. In that case extra cost for correcting the body is $30,000. Thus total cost of $10,000+$30,000=$40,000 has a probability of 10%.
Above three situation of further failure is covering 80% probability. Balance 20% chance exist when it will operate smoothly after repair. In that case only cost is $10,000. Considering all the situations together, expected cost is
0.4 x $20,000 + 0.3 x $30,000 + 0.1 x $40,000 + 0.2 x $10,000 = $23,000
--------------------------------------------------------------------------------------------------------------------------
Alternative 3: If the position is left alone then there is more than 100% probability that system will fail. There is 60% chance of failure of valve sheet. In that situation it has to incur a cost of $10,000.
There is 50% chance that valve stem will fail. In that case cost will be $20,000.
Finally there is 40% chance that valve body will fail. In that case cost will be $30,000. Thus average cost of correcting them will be:
(0.6 x $10,000) + (0.5 x $20,000) +(0.4 x $30,000) / (0.6+0.5+0.4) = $28,000 / 1.5 = $18,667
--------------------------------------------------------------------------------------------------------------------------------------------
Result: Compare above three alternatives. You will observe that expected cost of third one is lowest. So it is better to left it as it is for minimizing expected cost.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.