Nast Inc. is considering Projects S and L, whose cash flows are shown below. The
ID: 2634165 • Letter: N
Question
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost.
WACC: 8%
Year
0
1
2
3
4
CFS
-$1,100
$380
$380
$380
$380
CFL
-$2,200
$730
$730
$730
$730
$39.45
$42.83
$48.56
$53.70
$59.24
Year
0
1
2
3
4
CFS
-$1,100
$380
$380
$380
$380
CFL
-$2,200
$730
$730
$730
$730
Explanation / Answer
Alternative - 1 ar CFS CFL 0 1.00 ($1,100) ($1,100) ($2,200) ($2,200) 1 0.93 $380 $352 $730 $676 2 0.86 $380 $326 $730 $626 3 0.79 $380 $302 $730 $579 4 0.74 $380 $279 $730 $537 14.32% $159 12.37% $218 $59.24 IRR IRR Alternative - 2 differential NPV 0 1.00 ($1,100) -1100.0 1 0.93 $350 324.1 2 0.86 $350 300.1 3 0.79 $350 277.8 4 0.74 $350 257.3 59.244 ANSWER IS 59.24
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.