A project under consideration has an internal rate of return of 13% and a beta of 0.6. The risk-free rate is 8%, and the expected rate of return on the market portfolio is 13%. a-1. Calculate the required return. Required return % a-2. Should the project be accepted? Yes No b-1. Calculate the required return if its beta is 1.6. Required return % b-2. Should the project be accepted? Yes No A project under consideration has an internal rate of return of 13% and a beta of 0.6. The risk-free rate is 8%, and the expected rate of return on the market portfolio is 13%.Explanation / Answer
a. 0.08+ 0.6 (0.13 - 0.08)
= 0.11 or 11%
b.accept the project, because the real income is higher than expected one.
c. if the beta value is 1.6, then
= 0.08+ 1.6 (0.13 - 0.08)
= 0.16 or 16%
d. Accept the project
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.