You are considering 3 independent projects, project A, project B, and project C.
ID: 2632718 • Letter: Y
Question
You are considering 3 independent projects, project A, project B, and project C. Given the following cash flow information, calculate the payback period for each
If you require a 3-year payback before an investment can be accepted, which project(s) would be accepted?
Full Point will be given for work shown
Project A Project B Project C Initial Outlay -1,000 -10,000 -5,000 Inflow Yr 1 600 5,000 1,000 Inflow Yr 2 300 3,000 1,000 Inflow Yr 3 200 3,000 2,000 Inflow Yr 4 100 3,000 2,000 Inflow Yr 5 500 3,000 2,000Explanation / Answer
Payback period for project A:
payback period = 2+(100/200)
=2.5 years
----------------------------------------------------------------------------------------------------
Payback period for project B:
Payback period = 2+(2000/3000)
=2.67 years
-----------------------------------------------------------------------------------------
payback period for project C:
Payback period = 3+(1000/2000)
=3.5 years
Hence, project A should be accepted as its payback period is the lowest
Year cash flow Cumulative cash flow 0 -1,000 -1,000 1 600 -400 2 300 -100 3 200 100 4 100 200 5 500 700Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.