What is the IRR of Project X? (Do not round intermediate calculations. Enter you

ID: 2629491 • Letter: W

Question



What is the IRR of Project X? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).)



What is the IRR of Project Y? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).)



What is the crossover rate for these two projects? Hint: see the crossover rate in my Excel file. (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).)


  

Consider the following two mutually exclusive projects:

Explanation / Answer

a) For IRR, NPV=0

-16100 + 6690/(1+IRR) + 7270/(1+IRR)^2 + 4790/(1+IRR)^3 =0

IRR = 8.47%

b) For IRR, NPV=0

-16100 + 7250/(1+IRR) + 7750/(1+IRR)^2 + 3590/(1+IRR)^3 =0

IRR = 8.41%

c) For crossover rate, NPV of X= NPV of Y

-16100 + 6690/(1+R) + 7270/(1+R)^2 + 4790/(1+R)^3= -16100 + 7250/(1+IR) + 7750/(1+IR)^2 + 3590/(1+IR)^3

R= 9.67%