Abagail Corp. uses activity-based costing system with three activity cost pools. The following information is provided:
Costs: Wages and salaries $ 209,000
Depreciation 113,000
Utilities 114,000
Total $440,000
Activity Cost Pools
Assembly Setting Up Other
Wages and salaries 0.57 30% 10%
Depreciation 0.37 45% 20%
Utilities 0.21 40% 30%
How much total cost would be allocated to the Assembly activity cost pool?
Explanation / Answer
Hi,
Please find the detailed answer as follows:
Total Cost Allocated to Assembly = Wages and Salaries*% Allocated to Assembly + Depreciation*% Allocated to Assembly + Utilities*% Allocated to Assembly = 209000*57% + 113000*37% + 114000*21% = 184880
Answer is $184880.