Table 1 t A B C D 0 (13,900,000 ) (18,500,000) (10,500,000) (16,500,000 ) 1 5,17
ID: 2621350 • Letter: T
Question
Table 1
t A B C D
0 (13,900,000 ) (18,500,000) (10,500,000) (16,500,000 )
1 5,170,000 3,700,000 2,690,000 3,400,000
2 5,170,000 7,900,000 3,870,000 5,900,000
3 5,170,000 7,250,000 4,760,000 6,800,000
4 5,170,000 6,500,000 3,870,000 6,800,000
Risk High Average Low Average
I/ Y 12.03% 9.03% 6.53% 9.03
1. What is the NPV, IRR and MIRR for A,B,C &D?
2. Which of the projects are unacceptable and why?
3. Rank the projects that are acceptable, according to Mark