5. You are in charge of the resources part of a project. A new task in the proje

ID: 2621132 • Letter: 5

Question

5. You are in charge of the resources part of a project. A new task in the project will start on July 2nd, 2018, that is so close now. And it needs to be finished in the budget of $30K, but the planner doesn't decide the amount and duration yet. So all the information you get is that it takes $300 per labor per day and the reasonable range of the task's duration is 2 months. Now you need to contact the worker service company to send workers for that task from its beginning, but they need a clear number of labor and its time interval in calendar day. How can you tell them? Calculate and explain it.

Explanation / Answer

Budget =$30,000

Charges per labor per day=$300

Budget =30000/300=100 labor day

Task duration =2 months

Labor days required per month=100/2=50

Number of working days in a month =25

Number of labor required per day=50/25=2

Number of labor required per day=2

Duration =2 months

Number of days labor required =25 days per month