5. You are in charge of the resources part of a project. A new task in the proje
ID: 2621132 • Letter: 5
Question
5. You are in charge of the resources part of a project. A new task in the project will start on July 2nd, 2018, that is so close now. And it needs to be finished in the budget of $30K, but the planner doesn't decide the amount and duration yet. So all the information you get is that it takes $300 per labor per day and the reasonable range of the task's duration is 2 months. Now you need to contact the worker service company to send workers for that task from its beginning, but they need a clear number of labor and its time interval in calendar day. How can you tell them? Calculate and explain it.Explanation / Answer
Budget =$30,000
Charges per labor per day=$300
Budget =30000/300=100 labor day
Task duration =2 months
Labor days required per month=100/2=50
Number of working days in a month =25
Number of labor required per day=50/25=2
Number of labor required per day=2
Duration =2 months
Number of days labor required =25 days per month
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.