Last month, Standard Systems analyzed the project whose cash flows are shown bel
ID: 2620021 • Letter: L
Question
Last month, Standard Systems analyzed the project whose cash flows are shown below. However, before the decision to accept or reject the project took place, the Federal Reserve changed interest rates and therefore the firm's cost of capital (r). The Fed's action did not affect the forecasted cash flows. By how much did the change in the r affect the project's forecasted NPV? Note that a project's expected NPV can be negative, in which case it should be rejected.
11.25%
0
1
2
3
?$1,000
$410
$410
$410
Old r. 10.00% New r.11.25%
Year0
1
2
3
Cash flows?$1,000
$410
$410
$410
Explanation / Answer
NPV = Present value of cash inflows - present value of cash outflows
NPV when WACC is 10%:
NPV = -1000 + 410 / ( 1 + 0.1)1 + 410 / ( 1 + 0.1)2 + 410 / ( 1 + 0.1)3
NPV = 19.6093
NPV when WACC is 11.25%:
NPV = -1000 + 410 / ( 1 + 0.1125)1 + 410 / ( 1 + 0.1125)2 + 410 / ( 1 + 0.1125)3
NPV = -2.4174
Change in NPV = 19.6093 + 2.4174
Change in NPV = 22.03
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.