The overhead costs for a company are presently SX per month. The management team
ID: 2617256 • Letter: T
Question
The overhead costs for a company are presently SX per month. The management team of the company, in cooperation with the employees, is ready to implement a comprehensive improvement program to reduce these costs. If you (a) consider an observation of actual overhead costs for one month analogous to an output unit, (b) estimate the overhead costs for the first month of program implementation to be 1.2X due to extra front-end effort, and (c) consider a 86% improvement curve applicable to the situation, what is your estimate of the percentage reduction in present overhead costs after 28 months of program implementation? The percentage reduction in present overhead costs per month after 28 months of the program implementation is %. Round to one decimal place.)Explanation / Answer
From the problem introduction, we know that
:K=1.25X
s=0.85
Thus we have that
n=log0.85 / log2
= -0.234
Apply the learning-curve model in Eq.
Z36= 1.25X * 36-0.234= 0.54X
Thus the cost reduction by the program is
(1-0.54)=46%.
46%
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.