Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Your firm is contemplating the purchase of a new $943,500 computer-based order e

ID: 2616439 • Letter: Y

Question

Your firm is contemplating the purchase of a new $943,500 computer-based order entry system. The system will be depreciated straight-line to zero over its 5-year life. It will be worth $91,800 at the end of that time. You will be able to reduce working capital by $127,500 (this is a one-time reduction). The tax rate is 31 percent and your required return on the project is 22 percent and your pretax cost savings are $425,250 per year.

At what level of pretax cost savings would you be indifferent between accepting the project and not accepting it?

Your firm is contemplating the purchase of a new $943,500 computer-based order entry system. The system will be depreciated straight-line to zero over its 5-year life. It will be worth $91,800 at the end of that time. You will be able to reduce working capital by $127,500 (this is a one-time reduction). The tax rate is 31 percent and your required return on the project is 22 percent and your pretax cost savings are $425,250 per year.

Explanation / Answer

a). First we will calculate the annual depreciation of the new equipment. It will be:

Annual depreciation charge = $943,500/5

Annual depreciation charge = $188,700

The aftertax salvage value of the equipment is:

Aftertax salvage value = $91,800(1 ? 0.31)

Aftertax salvage value = $63,342

To evaluate the project with a $425,250 cost savings, we need the OCF to compute the NPV. Using the tax shield approach, the OCF is:

OCF = $425,250(1 ? 0.31) + 0.31($188,700) = $351,919.50

NPV = ?$943,500 + 127,500 + $351,919.50(PVIFA22%,5) + [($63,342 ? 127,500) / (1.22)5]

NPV = ?$943,500 + 127,500 + ($351,919.50 * 2.8636) + [-64,158/1.225]

= $168,018.2682

b). The NPV with a $306,200 cost savings is:

OCF = $306,200(1 ? 0.31) + 0.31($188,700) = $269,775

NPV = ?$943,500 + 127,500 + $269,775(PVIFA22%,5) + [($63,342 ? 127,500) / (1.22)5]

NPV = ?$943,500 + 127,500 + ($269,775 * 2.8636) + [-64,158/1.225]

NPV = ?$67,210.72204

We would accept the project if cost savings were $425,250, and reject the project if the cost savings were $306,200.

c). The required pretax cost savings that would make us indifferent about the project is the cost savings that results in a zero NPV. The NPV of the project is:

NPV = 0 = ?$943,500 + 127,500 + OCF(PVIFA22%,5) + [($63,342 ? 127,500) / (1.22)5]

Solving for the OCF, we find the necessary OCF for zero NPV is:

0 = ?$943,500 + 127,500 + (OCF * 2.8636) + [-64,158/1.225]

OCF = $839,738.412 / 2.8636

OCF = $293,245.71

Using the tax shield approach to calculating OCF, we get:

OCF = $293,245.71 = (S ? C)(1 ? 0.31) + 0.31($188,700)

(S ? C) = $234,748.71/0.69

(S - C) = $340,215.52

The cost savings that will make us indifferent is $340,215.52

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at drjack9650@gmail.com
Chat Now And Get Quote