You are contemplating investing into two different projects. Both projects are o

ID: 2614094 • Letter: Y

Question

You are contemplating investing into two different projects. Both projects are of equally low risk and their cash flows are provided below.

Year

Project “Gold”

Project “Blue”

0

-$50,000

-$25,000

1

$22,500

$3,000

2

$18,750

$6,000

3

$15,250

$12,000

4

$15,000

$24,000

Determine the NPV of each project at a 6% cost of capital. Which is preferable?

Based on the profitability index, which would you prefer?

At what discount rate would you be indifferent between the projects (i.e., calculate the crossover rate)?

Graphically illustrate what an NPV Profile Chart would look like (generally) if a crossover rate exists? Include the crossover rate calculated (step c), the NPV’s from (step a) and other appropriate labels for the axes, and project plots, etc.

Year

Project “Gold”

Project “Blue”

0

-$50,000

-$25,000

1

$22,500

$3,000

2

$18,750

$6,000

3

$15,250

$12,000

4

$15,000

$24,000

Explanation / Answer

Project Gold

Project Blue

Year

PV factors @6%

Cash flow

PV of cash flow

Cash flow

PV of cash flow

0

1.0000

-50000

-50000

-25000

-25000

1

0.9434

22500

21226

3000

2830

2

0.8900

18750

16687

6000

5340

3

0.8396

15250

12804

12000

10075

4

0.7921

15000

11881

24000

19010

NPV

12599

12256

According to NPV Project Gold is preferable

Profitablity Index of Project Gold is

PV of Cash in flows/PV of Cash outflows

=

1.251988947

Profitablity Index of Project Gold is

=

1.490233865

According to Profitability Index Project Blue is preferable

Coss Over rate calculation

For example take the interest rate of 10% and 7%

Year

Project Gold

Project Blue

Difference in cash flows

PV factor @10%

PV cashflow @10%

PV factor @7%

PV cashflow @7%

0

-50000

-25000

-25000

1

-25000

1

-25000

1

22500

3000

19500

0.909

17727.27

0.935

18224.30

2

18750

6000

12750

0.826

10537.19

0.873

11136.34

3

15250

12000

3250

0.751

2441.77

0.816

2652.97

4

15000

24000

-9000

0.683

-6147.12

0.763

-6866.06

-440.89

147.55

Cross over rate

7.75

                                                           

Project Gold

Project Blue

Year

PV factors @6%

Cash flow

PV of cash flow

Cash flow

PV of cash flow

0

1.0000

-50000

-50000

-25000

-25000

1

0.9434

22500

21226

3000

2830

2

0.8900

18750

16687

6000

5340

3

0.8396

15250

12804

12000

10075

4

0.7921

15000

11881

24000

19010

NPV

12599

12256

According to NPV Project Gold is preferable

Profitablity Index of Project Gold is

PV of Cash in flows/PV of Cash outflows

=

1.251988947

Profitablity Index of Project Gold is

=

1.490233865

According to Profitability Index Project Blue is preferable

Coss Over rate calculation

For example take the interest rate of 10% and 7%

Year

Project Gold

Project Blue

Difference in cash flows

PV factor @10%

PV cashflow @10%

PV factor @7%

PV cashflow @7%

0

-50000

-25000

-25000

1

-25000

1

-25000

1

22500

3000

19500

0.909

17727.27

0.935

18224.30

2

18750

6000

12750

0.826

10537.19

0.873

11136.34

3

15250

12000

3250

0.751

2441.77

0.816

2652.97

4

15000

24000

-9000

0.683

-6147.12

0.763

-6866.06

-440.89

147.55

Cross over rate

7.75