A project that provides annual cash flows of $2,500 for nine years costs $10,300
ID: 2613584 • Letter: A
Question
A project that provides annual cash flows of $2,500 for nine years costs $10,300 today.
At a required return of 10 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)
At a required return of 26 percent, what is the NPV of the project? (Do not round intermediate calculations. A negative amount should be indicated by a minus sign. Round your answer to 2 decimal places (e.g., 32.16).)
At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).
Requirement 1:At a required return of 10 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)
Explanation / Answer
A project that provides annual cash flows of $2,500 for nine years costs $10,300 today.
Requirement 1:
At a required return of 10 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)
NPV = -Initial Investment + Annual Cash Flow *((1+i)^n-1)/(i*(1+i)^n)
NPV = - 10300 + 2500*((1+10%)^9-1)/(10%*(1+10%)^9)
NPV = $ 4097.56
Requirement 2:
At a required return of 26 percent, what is the NPV of the project? (Do not round intermediate calculations. A negative amount should be indicated by a minus sign. Round your answer to 2 decimal places (e.g., 32.16).)
NPV = -Initial Investment + Annual Cash Flow *((1+i)^n-1)/(i*(1+i)^n)
NPV = - 10300 + 2500*((1+26%)^9-1)/(26%*(1+26%)^9)
NPV = - $ 1885.86
Requirement 3:
At what discount rate would you be indifferent between accepting the project and rejecting it? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).
Discounting rate (indifferent between accepting the project and rejecting it) = rate(nper,pmt,pv,fv)
Discounting rate (indifferent between accepting the project and rejecting it) = rate(9,2500,-10300,0)
Discounting rate (indifferent between accepting the project and rejecting it) = 19.32%
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.