The following table shows the standard cost for producing one of the most demand
ID: 2612994 • Letter: T
Question
The following table shows the standard cost for producing one of the most demanded products company
When the budget was prepared master this was based on a planned production of 3,000 products. Actual results are:
• Current production was 2,000 products.
• were purchased and 14,000 ounces of direct materials used at a total cost of $ 8.400.
• The total direct labor hand was $ 33.550 and 1.100 hours invested.
• The variable overhead cost was $ 12.980.
• The fixed overhead cost was $ 14,000.
Requested:
Calculate the following variances and indicate whether they were favorable (F) or unfavorable (U):
1. Variances in direct material:
to. Direct materials price variance
b. Direct materials quantity variance
c. Direct materials spending variance
2. Variances in direct labor:
to. Direct labor rate variance
b. Direct labor efficiency variance
c. Direct labor spending variance
3. Variances in variable overhead costs:
to. Variable overhead rate variance
b. Variable overhead efficiency variance
c. Variable overhead spending variance
4. Variances in fixed overhead costs:
to. Fixed overhead spending variance
b. Fixed overhead volume variance
*** PLEASE INCLUDE ALL THE CALCULATION OF THE PROBLEMS, THAK :)
Manufacturing costs Standard Quantity Standard Price (rate) Standard Unit Cost Direct Materials Direct Labor Manufacturing Overhead Costs: 7 onzas $0.50 por onza $3.50 0.60 horas $30.00 por hora $18.00 Variable (basado en mano de0.60 horas $10.00 por hora $6.00 obra directa) Fixed $15,000/3,000 unidades = $5 por unidad $5.00 Standard manufacturing cost per unit $32.50Explanation / Answer
1)
A) Materials price variance = (Actual price - Standard Price) *Actual Quantity
Materials price variance = (8400/14000 - 0.50)*14000
Materials price variance = $ 1400 Unfavorable
B). Materials usage/quantity variance = (Actual Quantity Used- Standard Quantity)Standard Price
Materials usage/quantity variance = (14000-7*2000)*0.50
Materials usage/quantity variance = None
c) Total Materials Spending variance = ( Actual price*Actual Quantity - Standard Price*Standard Quantity)
Total Materials Spending variance = (8400-0.5*7*2000)
Total Materials Spending variance = $ 1400 Unfavorable
2)
A) Labor rate variance = (Actual Rate-Standard Rate)*Actual Hour
Labor rate variance = (33550/1100 - 30)*1100
Labor rate variance = $ 550 Unfavorable
B) Labor efficiency variance = (Actual Hour-Standard Hour )Standard Rate
Labor efficiency variance = (1100-2000*0.6)*30
Labor efficiency variance = 3000 Favorable
c)
Direct labor spending variance= (Actual Rate*Actual Hour - Standard Rate* Standard Hour)
Direct labor spending variance = (33550 - 30*2000*0.6)
Direct labor spending variance = $ 2450 favorable
3)
A) Variable Overhead rate variance = (Actual Rate-Standard Rate)*Actual Hour
Variable Overhead rate variance = (12980/1100 - 10)*1100
Variable Overhead rate variance = $ 1980 Unfavorable
B) Variable Overhead efficiency variance =(Actual Hour-Standard Hour )Standard Rate
Variable Overhead efficiency variance = (1100 - 2000*0.6)*10
Variable Overhead efficiency variance = 1000 Favorable
c) Variable overhead spending variance= (Actual Rate*Actual Hour - Standard Rate* Standard Hour)
Variable overhead spending variance = (12980 - 10*2000*0.6)
Variable overhead spending variance = $ 980 Unfavorable
4)
a) Fixed overhead spending variance = Actual Fixed Overhead - Budgeted Fixed Overhead
Fixed overhead spending variance = 14000 - 15000
Fixed overhead spending variance = 1000 Favorable
b) Fixed overhead volume variance = ( Budgeted Fixed Overhead - Standard Unit * Standard Rate)
Fixed overhead volume variance = (15000 - 2000*5)
Fixed overhead volume variance = $ 5000 Unfavorable
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.