Question 2. Considering the following data for a project begun in 2017 by Domini
ID: 2611564 • Letter: Q
Question
Question 2. Considering the following data for a project begun in 2017 by Dominion Construction, with a contract price of $1,500,000. Dominion uses IFRS and their customer controls the building during the period of construction. 20172018 Current period costs Estimated additional costs to complete Progress billings Collection on billings-current year $200,000$200,000 400,000 150,000 700,000 40 175,000 100,000100,000 Using the table below, calculate the revenue to be recognized by Dominion Construction during 2017 and 2018. Assume that percentage of completion is measured by the ratio of costs incurred to date divided by total estimated construction costs. Round your percentage complete calculations to one decimal place. Using the information in your table, prepare all of the required journal entries for 2017 only. Year(s) 2017 2018Explanation / Answer
1. Calculation of Revenue to be recognized in both years.
2017:
Percentage of Completion = Total costs incurred in 2017 / estimated cost of construction
Total cost incurred in 2017 = 200,000
Total Estimated costs = 200,000 + 700,000 = 900,000
Percentage of Completion in 2017 = 200,000 / 900,000 = 22.2%
Revenue to be booked in 2017 = Total contract price x percentage of completion
= 1,500,000 x 22.2% = $333,000
2018:
Percentage of completion = (200,000 + 200,000) / (200,000 + 200,000 + 400,000)
= 50%
Total Revenue to be booked = 1,500,000 x 50% = $750,000
Revenue already booked in 2017 = $333,000
Revenue to be booked in 2018 = 750,000 - 333,000 = $417,000
C. Journal Entries for 2017
Date
Particulars
Debit
Credit
1
Construction in progress
TO Accounts Payable
(Being entry for costs incurred in 2017)
200,000
200,000
2
Construction in progress
Expenses
TO Revenue
(NOTE 1)
133,000
200,000
333,000
3
Accounts Receivable
TO Billings on construction contract
(Being billings made to client)
175,000
175,000
4
Cash
TO Accounts Receivable
(Being amount collected from customer)
100,000
100,000
NOTE 1: Journal entry for recording the revenue under percentage completion.
Revenue account will be credited by $333,000 calculated in part a. Out of total 333,000 amount of $200,00 is actual expense incurred in current year and the same will be booked as expense and debited in journal entry. Whereas, remaining amount of $133,000 will be debited in Construction in progress control account.
Date
Particulars
Debit
Credit
1
Construction in progress
TO Accounts Payable
(Being entry for costs incurred in 2017)
200,000
200,000
2
Construction in progress
Expenses
TO Revenue
(NOTE 1)
133,000
200,000
333,000
3
Accounts Receivable
TO Billings on construction contract
(Being billings made to client)
175,000
175,000
4
Cash
TO Accounts Receivable
(Being amount collected from customer)
100,000
100,000
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.