Problem 4 Early in 2012, Dobbs Corporation engaged Kiner, Inc. to design and con
ID: 2601626 • Letter: P
Question
Problem 4
Early in 2012, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on Jan. 2, 2012 and was completed on December 31, 2012. Dobbs made the following payments to Kiner, Inc. during 2012:
Date Payment
January 2, 2012 $1,200,000
June 1, 2012 3,600,000
August 31, 2012 6,000,000
December 31, 2012 6,000,000
In order to help finance the construction, Dobbs issued the following during 2012:
1. $4,000,000 of 10-year, 9% bonds payable, issued at par on May 31, 2012, with interest payable annually on May 31.
2. 1,000,000 shares of no-par common stock, issued at $10 per share on October 1, 2012.
In addition to the 9% bonds payable, the only debt outstanding during 2012 was a $1,000,000, 12% note payable dated January 1, 2008 and due January 1, 2018, with interest payable annually on January 1.
Instructions
Compute the amounts of each of the following (show computations):
1. Weighted-average accumulated expenditures qualifying for capitalization of interest cost.
2. Avoidable interest incurred during 2012.
3. Total amount of interest cost to be capitalized during 2012.
Explanation / Answer
1 Date Capitalization Expenditures Period Weighted-Average Accumulated Expenditures January 2 $ 1,200,000 12/12 $ 1,200,000 June 1 3,600,000 7/12 2,100,000 August 31 6,000,000 4/12 2,000,000 December 31 6,000,000 0 0 Ans 1 $ 5,300,000 2 Weighted-Average Accumulated Expenditures Appropriate Interest Rate Avoidable Interest $4,000,000 9% 360,000 $1,300,000 12% 156,000 $5,300,000 $ 516,000 Ans 2 3 Actual Interest incurred during 2012 9% bonds payable, $4,000,000 x .09 x 7/12 210,000 12% note payable, $1,000,000 x .12 120,000 Ans 3 $ 330,000 The interset cost to be capitalized is $330,000 (the lesser of the $516,000 Avoidable interest and the $330,000 actual interest cost)
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.