On March 31,2018, M. Belotti purchased the right to remove gravel from an old rock quarry. The gravel is to be sold as roadbed for highway construction. The cost of the quarry rights was $184,800, with estimated salable rock of 24,000 tons. During 2018, Belotti loaded and sold 4,100 tons of rock and estimated that 19,900 tons remained at December 31, 2018. At January 1, 2019, Belotti estimated that 12,300 tons still remained. During 2019, Belotti loaded and sold 8,200 tons. Belotti uses the units-of-production method. Belotti would record depletion in 2019 of. (Round cost per ton to two decimal places.) Multiple Choice $102,172 $105,452. $115,292Explanation / Answer
Belotti would record depeltion in 2018 = 184800 X (4100/24000) = $31570
Belotti would record depeltion in 2019 =
Depletion per unit = (184800-31570) /12300) = $12.46
Belotti would record depeltion in 2019 = 8200 X 12.46 = $102172
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.