Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Exercise 24-7 Iggy Company is considering three capital expenditure projects. Re

ID: 2596449 • Letter: E

Question

Exercise 24-7 Iggy Company is considering three capital expenditure projects. Relevant data for the projects are as follows Annual Life of ProjectInvestment Income Project $244,100 $17,140 6 years 273,500 20,740 9 years 280,600 15,700 7 years 22A 23A 24A Annual income is constant over the life of the project. Each project is expected to have zero salvage value at the end of the project. Iggy Company uses the straight-line method of depreciation. Click here to view Py takle Determine the internal rate of return for each project. (Round answers 0 decimal places, e.g. 10. For calculation purposes, use 5 decimal places as displayed in the factor table provided.) Project Internal Rate of 22A 23A 24A Return If Iggy Company's required rate of return is 11%, which projects are acceptable? The following project(s) are acceptable

Explanation / Answer

Internal rate of return is the rate at which if we discount all the future cash flows, the resulting NPV will be zero, it is minimum rate of return that management seeks from the project, IRR of the asset/project must be greater than the required rate of return, otherwise it will not be feasible for the management to accept the project. Best way to calculate IRR is using Excel.

--------------------------------------------------------------------------------------------------------------------------------

Project

22A

23A

24A

Initial cost

244100

273500

280600

Annual depreciation

40683.33

30388.89

40085.71

Net income

17140

20740

15700

Operating cash flow

57823.33

51128.89

55785.71

IRR

22A

23A

24A

Initial cash out flow

-244100

-273500

-280600

Annual cash inflow (1)

57823.33

51128.89

55785.71

2

57823.33

51128.89

55785.71

3

57823.33

51128.89

55785.71

4

57823.33

51128.89

55785.71

5

57823.33

51128.89

55785.71

6

57823.33

51128.89

55785.71

7

51128.89

55785.71

8

51128.89

9

51128.89

IRR

11.07%

11.90%

9.02%

Formula

=IRR(B10:B19)

Project 22A and 23A has IRR above required rate

Project 23A has highest IRR so it should be selected.

--------------------------------------------------------------------------------------------------------------------------------

Hope that helps.

Feel free to comment if you need further assistance J

Project

22A

23A

24A

Initial cost

244100

273500

280600

Annual depreciation

40683.33

30388.89

40085.71

Net income

17140

20740

15700

Operating cash flow

57823.33

51128.89

55785.71

IRR

22A

23A

24A

Initial cash out flow

-244100

-273500

-280600

Annual cash inflow (1)

57823.33

51128.89

55785.71

2

57823.33

51128.89

55785.71

3

57823.33

51128.89

55785.71

4

57823.33

51128.89

55785.71

5

57823.33

51128.89

55785.71

6

57823.33

51128.89

55785.71

7

51128.89

55785.71

8

51128.89

9

51128.89

IRR

11.07%

11.90%

9.02%

Formula

=IRR(B10:B19)