Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Beck Construction Company began work on a new building project on January 1, 201

ID: 2595104 • Letter: B

Question

Beck Construction Company began work on a new building project on January 1, 2017. The project is to be completed by December 31, 2019, for a fixed price of $114 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years Actual costs incurred in each year Estimated remaining costs to complete the project (measured at Dec. 31 of each year) 2017 $ 32 million $ 64 million 2018 $ 49 million $ 49 million 2019 $ 37 million $ 0 Required: What amount of gross profit (or loss) would Beck record on this project in each year, assuming that Beck recognizes revenue for this project upon completion of the project? Place answers in the spaces provided below and show supporting computations. (Loss amounts should be indicated with a minus sign. Enter your answers in millions (i.e., 10,000,000 should be entered as 10).)

Explanation / Answer

114

Price of the project at the end of december 31' 2019 $ 114 Million ($ in million) Particulars 2017 2018 2019 Previous year cost                -                     32                       81 Actual Cost               32                   49                       37 Total cost incurred               32                   81                    118 Estimated remaining cost               64                   49                        -   Total project cost estimated               96                 130                    118 Fixed price of the project

114

                114                    114 Estimated profit               18                 (16)                       (4) Gross profit/(Loss) to be recognised                 6                 (10)                       (0) (Estimated profit/Total projected Cost estimated* total cost incurred) Note: Revenue recognition at the time of completion will be after setting of previous years loss or profit
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote