Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Overhead is applied on the basis of direct labor hours. Three direct labor hours

ID: 2594885 • Letter: O

Question

Overhead is applied on the basis of direct labor hours. Three direct labor hours are required for each product unit.
Planned production for the period was set at 8,000 units. Manufacturing overhead for the period is budgeted at
$204,000, of which 30 percent is fixed. The 26,200 hours worked during the period resulted in production of8,500
units. Manufacturing overhead cost incurred was $220,500.
Required:
Using the spreadsheet provided on the following page, calculate the following variances:
a. Overhead spending variance
b. Overhead efficiency variance
c. Overhead volume variance
d. Total overhead variance
e. Interpret your results

Explanation / Answer

Solution:

1 unit

3

hours

Reqd Hours

24,000

Production

8,000

units

Budgeted

Manufacturingfacturing Overhead

204,000

Fixed

0.3

Fixed Manufacturing Overhead

61,200

2.55

61200/24000 = 2.55

Variable Manufacturing Overhead

142,800

5.95

142800/24000 = 5.95

Actual Manufacturing Overhead

220,500

Actual Hours wrkd

26,200

Actual Production

8,500

a. Overhead spending variance

Overhead Spending Variance

Actual Manufacturing Overhead

220,500

Actual Hours wrkd

26,200

Actual Production

8,500

Std Hours for one unit

3

Standard FOverhead rate:

Variable

5.95

Fixed

2.55

Actual FOverhead

220,500

Budgeted allowance based on acutal Hours worked:

Fixed exp budgeted

61,200

Allowed Vari Overhead

155,890

Spending Variance

3,410

Unfavorable

Interpret: It reflects that the spending as per the standard rate for actual hours exceed to the actual amount spend . Thus the result is Favourable.

b. Overhead efficiency variance

Actual Hours worked at std rate

222,700

Overhead charged to production

216,750

Effeciency Variance

5,950

Unfavorable

Interpretation : It reflects that more actual hours as compared to the standard hours for actual production so result is unfavorable.


c. Overhead volume variance

Fixed Expenses budgeted

61,200

variable expeneses

151,725

Budgeted Allowance

212,925

Overhead Charged to production

216,750

Volume Variance

-3,825

Favorable

Interpret: The volume produced exceeds the planned and therefore it is produced more than the planned production


d. Total overhead variance

Total Variable overhead variance = (Standard hours for actual production * Standard rate)- Actual Overhead

= (8500*3)*5.95 – 154350 = 2625 (Unfavorable)

Interpret. : The volume produced exceeds the planned and therefore it is produced more than the planned production

1 unit

3

hours

Reqd Hours

24,000

Production

8,000

units

Budgeted

Manufacturingfacturing Overhead

204,000

Fixed

0.3

Fixed Manufacturing Overhead

61,200

2.55

61200/24000 = 2.55

Variable Manufacturing Overhead

142,800

5.95

142800/24000 = 5.95

Actual Manufacturing Overhead

220,500

Actual Hours wrkd

26,200

Actual Production

8,500

Dr Jack
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Chat Now And Get Quote