Gerstein Corporation uses a job-order costing system with a single plantwide pre
ID: 2593957 • Letter: G
Question
Gerstein Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $90,000, variable manufacturing overhead of $3.70 per direct labor-hour, and 50,000 direct labor-hours. The company recently completed Job M800 which required 150 direct labor-hours.
The estimated total manufacturing overhead is closest to:
$90,000
$275,000
$185,000
$90,004
$90,000
$275,000
$185,000
$90,004
Explanation / Answer
Estimated total manufacturing overhead = 90000+(50000*3.7)= 275000 Option 2 is correct