Question
The auto repair shop Quality Motor Company uses standards to control the labor time and labor cost in the shop. The standard labor cost for a motor tune-up is given below:
Job Standard Hours Standard Rate Standard Cost
Motor tune-up 2.5 $9.00 $22.50
The record showing the time spent in the shop last week on motor tune-ups has been lost, however. The controller recalls the following variance data relating to tune-ups:
Labor Rate Variance $87 F
Spending Variance $93 U
What is the number of actual labor-hours spent on tune-ups during the week?
a. 7
b. 5
c. 21
d. 22.5
Explanation / Answer
Efficiency Variance = SR x ( AH - SH)
Standard Rate = $9
Standard hours = 50*2.5 = 125
Efficieny Variance = $87 F + $93U = $180
180 = 9 x ( AH - 125)
180 = 9AH - 1,125
9AH = 1305
AH = 1305/9 = 145 hours
Actual Hours worked = 145 hours