Question 14 (of 22)> | Save & Exit | | Submit Time remaining: 1:32:16 14 Shed In
ID: 2593375 • Letter: Q
Question
Question 14 (of 22)> | Save & Exit | | Submit Time remaining: 1:32:16 14 Shed Industries produces two products. The products' identified costs are as follows: Product A Product B $20,000 29,000 $25,000 Direct materials Direct labor 11,000 The company's overhead coss of $160,000 are allocated based on direct labor cost. Assume 9,000 units of product A and 10,000 units of Product B are produced. What is the cost per unit for product B? (Do not round intermediate calculations. Round your answer to 2 decimal places.) O $16.50 O $4.90 O $16.00 O None of these answers is correct.Explanation / Answer
STEP 1: Calculation of Overhead recovery rate Overhead cost is based on the direct labour Cost Direct Labour Cost = Labour Cost for Product A + Labour Cost for product B Direct Labour Cost = $ 11,000 + $ 29,000 = $ 40,000 Recovery Rate = Overhead Cost / Direct Labour Cost Recovery Rate = $ 160,000 / $ 40,000 Recovery Rate = $ 4.00 Step 2: CALCULATION OF THE COST OF THE PRODUCT B Material Cost $ 20,000 Direct Labour $ 29,000 Overhead Cost ( $ 29,000 X $ 4.00) $ 1,16,000.00 Total Cost $ 1,65,000 Number of units Produced = 10,000 Units Cost per Unit = Total Cost / Number of Units Produced Cost per Unit = $ 165,000 / 10,000 Units Cost per Unit = $ 16.50 Per unit Answer = Option 1 = $ 16.50
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.