Fremont, inc., builds storage boxes to custom order. Materials include 20 board
ID: 2593321 • Letter: F
Question
Fremont, inc., builds storage boxes to custom order. Materials include 20 board feet of lumber oat $1.25/board foot. Standards call for 2 hours of labor at $15/hr. During March, 4,200 boxes were built. Materials pruchased toataled $103,890 for 86,300 board feet of lumber. Actual lumber usage in production was 82,310 boaard feet. The March payroll was $139,360 for 9,150 hours. Each answer needs to indicate if it is Favorable or Unfavorable.
a) Compute the direct material price variance.
b) Compute the direct material quantity variance.
c) Compute the direct labor rate variance.
d) Compute the direct labor efficiency variance.
Explanation / Answer
Standard Price (SP)
1.25
Standard Quantity (SQ)
20*4200
84000
Actual Price (AP)
103890/86300
1.20
Actual Quantity (AQ)
82310
Direct Material Price Variance
AQ *(SP - AP)
82310 *(1.25 - 1.20)
82310 *(0.05)
4115.5 Favourable
Direct Material Quantity Variance
SP *(SQ - AQ)
1.25 *(84000 - 82310)
1.25*1690
2112.50 Favourable
Standard Rate (SR)
15
Standard Hours (SH)
2*4200
8400
Actual Rate (AR)
139360/9150
15.23
Actual Hours (AH)
9150
Direct Labor Rate Variance
AH*(SR - AR)
9150 *(15 - 15.23)
9150 *(- 0.23)
2104.5 Unfavourable
Direct Labor Efficiency Variance
SR * (SH - AH)
15 * (8400 - 9150)
15*(-750)
11250 Unfavourable
Standard Price (SP)
1.25
Standard Quantity (SQ)
20*4200
84000
Actual Price (AP)
103890/86300
1.20
Actual Quantity (AQ)
82310