mathxl.com Take a Test- Mariajo. Unit 3: Annual Repor Home | Chegg.com A Corp ACC 221-N02 Fall 2017 Test:Test Chapters 17 18 19 This Question: 1 pt 140f 48 (13 complete) glesias, Inc. completed Job 12 on November 30. The details of Job 12 are given below Direct labor cost Direct materials cost Machine hours Direct labor hours Predetermined overhead allocation rate $900 $1,200 9 hours 24 hours $80 per machine hour What is the total cost of Job 127 O A $2,100 O B. $1,820 O C. $2,820 O D. $1,620 Click to select your answer

Explanation / Answer

Total cost=Direct labor+Direct material+Overheads

=$900+$1200+$(80*9)

which is equal to

=$2820.