Prather Corporation uses a job-order costing system with a single plantwide pred
ID: 2580092 • Letter: P
Question
Prather Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The compa based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 50,000 203Total fixed manufacturing overhead cost $285,000 3.80 Variable manufacturing overhead per direct labor-hour Recently, Job P513 was completed with the following characteristics Number of units in the job Total direct labor-hours Direct materials Direct labor cost 10 20 $710 $500 The estimated total manufacturing overhead is closest to: Multiple ChoiceExplanation / Answer
Answer: $475000
Total fixed manufacturing overhead cost = $285000
Total variable manufacturing overhead cost = 50000 DLH x $3.80 = $190000
Total manufacturing overhead = $285000 + $190000 = $475000
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.