Variance Analysis Project Use the following data to calculate the variances in problems 1-5. Standard Cost Profile Lab Treatment SU #12 Expected Treatments 1,000 Quantity Quantity Unit Variable Average Average Resource Variable Fixed Cost Cost Fixed Cost Total Cost Labor Supplies $ 25.60 0.80 7.00 0.80 $16.00 $ 12.80 12.80 1.10 7.70 Actual Month Cost Lab Treatment SU #12 Actual Treatments- 1,100 Quantity Total Unit UsedCost Cost Resource Labor 1,600 S 17.00 $27,200 1.00 7500 S34.700 Supplies 7,500 Calculate the following variances: 5. Volume VarianceExplanation / Answer
direct materials variance =
(Actual unit quantity consumed - Budgeted unit quantity consumed) x Budgeted cost per unit
(7500-7000)*7.7
=3850
Labor volume variance shall be calculated as follows:
= (1100*1.6 - 1600) * 25.6
= 4096
Where,
SH are the standard direct labor hours allowed for actual output
AH are the actual direct labor hours used
SR is the standard direct labor rate per hour