Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Kareena Company produced 2,200 buckets during October. The following variable ov

ID: 2577506 • Letter: K

Question

Kareena Company produced 2,200 buckets during October. The following variable overhead data pertains to October: (Don’t forget to designate if the variance is favorable or unfavorable)

  Actual           Budgeted
Production                                                    2,200 units         2,400 units
Total Machine-hours                                  8,800 hours        9,000 hours
Variable overhead cost per machine-hour            $6.25                  $7.00

a) What is the flexible-budget amount?
b) What is the variable overhead spending variance?
c) What is the variable overhead efficiency variance?

Explanation / Answer

a)

Flexible budget amount=Actual production*Machine hrs per bucket*budgeted cost per hr

=2,200buckets*(9000 hrs/2400)*$7.00

=$57,750

b)

Variable overhead spending variance

=Actual m.hrs*(Actual cost per m.hr-Budgeted cost per m.hr)

=8,800*(6.25-$7)

=$6,600 Favorable

c)

Variable overhead efficiency variance

=[(Actual production*budgted m.hr per bucket)-actual m.hrs]*Budgeted cost per m.hr

=[(2200*9000/2400)-8800]*$7

=$3,850 unfavorable