Use the following for the next five questions: The following data is given for t
ID: 2577159 • Letter: U
Question
Use the following for the next five questions: The following data is given for the Walker Company: Budgeted production...............................................1,000 units Actual production........................................................980 units Materials: Standard price per lb..................................................... ..$2.00 Standard pounds per completed unit....................................12 Actual pounds purchased and used in production.............11,800 Actual price paid for materials........................................$23,000 Labor: Standard hourly labor rate....................................$14 per hour Standard hours allowed per completed unit........................4.5 Actual labor hours worked................................................4,560 Actual total labor costs..................................................$62,928 The direct material price variance is: $600 F $600 U $80 F $80 U
Explanation / Answer
Formula: Direct material Price Variance = (Actual Price - Budgeted price)*Actual Quantity
= ($23,000 - $2*11,800)
Hence the option is A ie., 600F
Direct material price variance is 600F
Formula: Direct material Price Variance = (Actual Price - Budgeted price)*Actual Quantity
= ($23,000 - $2*11,800)
= ($23,000 - $23,600) = 600 FHence the option is A ie., 600F
Direct material price variance is 600F
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.