Delmar Inc. uses a standard cost system. Labor standards are 2.1 hours per widge
ID: 2576290 • Letter: D
Question
Delmar Inc. uses a standard cost system. Labor standards are 2.1 hours per widget at $9.10 per hour. During August, Delmar Inc. paid its workers $154,040 for 16,700 hours. Delmar Inc. produced 8,600 widgets during August a. Calculate the direct labor rate variance. (Do not round your intermediate calculations. Indicate the effect of variance by selecting "Favorable", "Unfavorable", or "None" for no effect i.e., zero variance).) Rate Variance b. Calculate the direct labor efficiency variance. (Indicate the effect of variance by selecting "Favorable", "Unfavorable", or "None" for no effect (i.e., zero variance).) Efficiency VarianceExplanation / Answer
Direct labor rate variance = (actual rate - standard rate) * actual hours
= ($9.22 - $9.10) * 16700 hours
= $2004 unfavourable.
Direct labor efficiency variance = (actual hours - standard hours) * standard rate
= (16700 hours - 18060 hours) * $9.10
= ($12376) favourable.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.