Support Departments Revenue departments Info System Facilities Computer Programs

ID: 2572228 • Letter: S

Question

Support Departments Revenue departments Info System Facilities Computer Programs Consulting Training Direct Costs $              50,000 $                 25,000 $              75,000 $                    110,000 $              85,000 Facilities (Sq Ft)                200,000                400,000                           60,000                800,000 Info Systems (hrs)                           400                    1,100                                600                       900 Total Cost Step Method $                      -   $                               -   $                      -   Total Cost Reciprocal Support Departments Revenue departments Info System Facilities Computer Programs Consulting Training Direct Costs $              50,000 $                 25,000 $              75,000 $                    110,000 $              85,000 Facilities (Sq Ft)                200,000                400,000                           60,000                800,000 Info Systems (hrs)                           400                    1,100                                600                       900 Total Cost Step Method $                      -   $                               -   $                      -   Total Cost Reciprocal

Explanation / Answer

Under step down method, unless other wise mentioned, first the costs of the those support departments whose cost is more is assigned first and then the other later.

Hence, first Infosystems costs are assigned which is as follows:

Total hours =3000 hours .

Cost per hour =$50,000/3000

=16.67 per hour.

After assigning the costs of infosystems to other departments, the costs are as follows:

Cost of facilities department=$31,668./1260000

Total square feet of facilities department=0.025133

Particulars Info systems Facilities Computer Programs Consulting Traning Direct costs 50000 25000 75000 110000 85000 Allocation of facilities cost to other departments 400 1100 600 900 Cost per of infosystmes per hour 16.67 16.67 16.67 16.67 Total costs of info systems assigned 6668 18337 10002 15003 Total costs before assigning facilities dept costs 31668 93337 120002 100003