Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and video systems for homes. On newly constructed homes it provides bids using time-and-material pricing. The following budgeted cost data are available.Time
Charges Material
Loading
Charges Technicians' wages and benefits $147,481 - Parts manager's salary and benefits - $33,400 Office employee's salary and benefits 26,646 16,790 Other overhead 15,911 40,726 Total budgeted costs $190,038 $90,916
The company has budgeted for 6,390 hours of technician time during the coming year. It desires a $37.68 profit margin per hour of labor and an 80% profit on parts. It estimates the total invoice cost of parts and materials in 2017 will be $717,000.
(a)
Your answer is correct. Compute the rate charged per hour of labor. (Round answer to 2 decimal places, e.g. 10.50.)Labor rate $ per hour Click if you would like to Show Work for this question:
Open Show Work
SHOW SOLUTION
SHOW ANSWER
LINK TO TEXT
Attempts: 1 of 5 used(b)
Compute the material loading percentage. (Round answer to 2 decimal places, e.g. 10.50.)Material loading percentage % Click if you would like to Show Work for this question:
Open Show Work
Explanation / Answer
a.
b.
Time charges per hour ($190038/ 6390) $29.74 Add profit margin 37.68 Labor rate $67.42 per hourRelated Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.