The following data is given for the Stringer Company Budgeted production Actual
ID: 2566845 • Letter: T
Question
The following data is given for the Stringer Company Budgeted production Actual production Materials: 26,000 units 27,500 units $6.50 Standard price per ounce Standard ounces per completed unit Actual ounces purchased and used in production Actual price paid for materials Labor: Standard hourly labor rate Standard hours allowed per completed unit Actual labor hours worked Actual total labor costs Overhead: Actual and budgeted fixed overhead Standard variable overhead rate Actual variable overhead costs 228,000 $1,504,800 $22 per hour 6.6 183,000 $4,020,000 $1,029,600 $24.50 per standard labor hour $4,520,000 Overhead is applied on standard labor hours. The direct materials price variance is a. $52,000 unfavorable b. $22,800 unfavorable Oc. $22,800 favorable d. $52,000 favorableExplanation / Answer
Answer is option (b) $22800 unfavourable
Explanation;
Formula for Direct Material Price Variance;
(Standard Price – Actual Price) * Actual Quantity Used
Standard price = $6.50 per ounce
Actual price is calculated as follow;
Actual price paid materials / Actual quantity used
= $1504800 / 228000 = $6.60 per ounce
Actual quantity used is given = 228000
Now put the values in the formula to know direct material price variance;
($6.50 – $6.60) * 228000
= - $0.10 * 228000
= $22800 (unfavourable)
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.