The Thomlin Company estimates that total overhead for the current year will be $
ID: 2565624 • Letter: T
Question
The Thomlin Company estimates that total overhead for the current year will be $17,000,000 and that total machine hours will be 200,000 hours. Year to date, the actual overhead is $17,500,000 and the actual machine hours are 220,000 hours. If the Thomlin Company uses a predetermined overhead rate based on machine hours for applying overhead, what is that overhead rate?
Question 11 options:
$88 per machine hour
$77 per machine hour
$85 per machine hour
$80 per machine hour
$88 per machine hour
$77 per machine hour
$85 per machine hour
$80 per machine hour
Explanation / Answer
predetermined overhead rate = Estimated total overhead / Estimated total machine hour
= $ 17,000,000 / 220,000 hours
= $ 85 per machine hour
Hence the correct answer is $ 85 per machine hour