Brothern Corporation bases its predetermined overhead rate on the estimated mach
ID: 2565127 • Letter: B
Question
Brothern Corporation bases its predetermined overhead rate on the estimated machine- hours for the upcoming year. Data for the most recently completed year appear below: Estimates made at the beginning of the year: Estimated machine-hours Estimated variable manufacturing overhead Estimated total fixed manufacturing overhead 39, 700 6.32 pe $1, 159, 637 37, 500 Actual machine-hours for the year The predetermined overhead rate for the recently completed year was closest to: Multiple Choice $6.32 per machine-hour $29.21 per machine-hour $35.53 per machine-hour $35.18 per machine-hourExplanation / Answer
Calculate predetermine overhead rate :
Fixed predetermine overhead rate = Estimated fixed manufacturing overhead/Estimated machine hour
= 1159637/39700
Fixed predetermine overhead rate = 29.21 per machine hour
Total predetermine overhead rate = (29.21+6.32) = 35.53 per machine hour
so answer is c) 35.53 per machine hour
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.