year R &D; project. The most recent 1.Your company is preparing a technical proposal for a one fiscal year has he following results for the year. Direct Materials Direct labor Overhead G & A Sales $2,445,000 $6,879,000 6,920,600 $ 1,578,100 20,432,200 Calculate the Overhead rate, the G & A rate and the profit margin as a percentage of annual factory cost. Using the rates calculated above, prepare a cost proposal for the following estimated cost factors. Direct materials: Consultants Direct labor: Senior engineer Engineer Technician $573,200 230,000 3,470 hrs @ $47.35/hr 4,335 hrs @ $38.50/hr 9,375 hrs @ $22.25/hr

Explanation / Answer

Factory cost is defined as the total cost which is required for the purposes of manufacturing goods. It is the sum total of direct materials, direct labour and manufacturing costs.

Hence, the factory cost would be calculated as follows:

Particulars

Amounts in $

Direct materials

     24,45,000.00

Direct labour

     68,79,000.00

Manufacturing overhead

     69,20,600.00

Total factory cost

   162,44,600.00

Formula used

Amount

Explanation

Overhead rate

Manufacturing overhead/Total factory cost

42.60%

6920600/16244600

G&A

G&A costs/total factory cost

9.71%

1578100/16244600

Calculation of profit margin

Particulars

Amounts in $

Direct materials

      24,45,000.00

Direct labour

      68,79,000.00

Manufacturing overhead

      69,20,600.00

G&A

      15,78,100.00

Total factory cost

    178,22,700.00

Sales

    204,32,200.00

Profit margin

      26,09,500.00

Profit margin

Net profit/Sales

12.77%

2609500/20432200

Preparation of cost proposal:

Amounts in $

Explanation

Formula used

Direct materials

          5,73,200.00

Consultants

          2,30,000.00

Direct labour:

Senior Engineer

          1,64,304.50

3470*47.35

Formula used number of hours given in question*rate per hour

Engineer

          1,66,897.50

4335*38.5

Formula used number of hours given in question*rate per hour

Technician

          2,08,593.75

9375*22.25

Formula used number of hours given in question*rate per hour

Welder

            66,978.00

2440*27.45

Formula used number of hours given in question*rate per hour

Total factory cost

     14,09,973.75

MLB+75000

Total factory cost+75000

     14,84,973.75

1409974+75000

Factory cost

     14,09,974.00

No the project should not be accepted since the project would only entail recovery of costs for the company and no profit

Factory cost

Total factory cost+50000

     14,59,973.75

1409974+50000

Yes the project should be accepted since the project would not only entail recovery of costs for the company but also profit for the company

Particulars

Amounts in $

Direct materials

     24,45,000.00

Direct labour

     68,79,000.00

Manufacturing overhead

     69,20,600.00

Total factory cost

   162,44,600.00

Formula used

Amount

Explanation

Overhead rate

Manufacturing overhead/Total factory cost

42.60%

6920600/16244600

G&A

G&A costs/total factory cost

9.71%

1578100/16244600